Setting out of building
As simple as setting out of a building may look majority of us do not bother to find out what it is all about
Setting out is simply the physical transfer into the ground what was initially on plan or in paperwork. Transfering the building professionals drawing (the architect) plan onto the ground is a process of setting out.
Setting out can be complex yet simple. For more accurate transfer some engineers uses the services of land surveyors to get their set out right especially in large projects. Theodolite is often used by the surveyor or any engineer that has a good knowledge of the application to get the level of a subject place in relation to a decided point around the building area.
But we are going to concern ourselves with the simple pegging which is common and later talk about setting out with using blocks.
Assuming you have a rectangular site of 50ft x100ft what you should take note first of is the four corners where we have your pillars. Put pegs at each points or very close in case you have disturbing concrete . After establishing these four corners put nails on top of each peg and then run rope round the 4 pegs.
Of course I need to tell you that you will get peg and thin wood (or tie rod] from the sawmills (the number required has been worked in your free sample estimate you get when you subscribed for my articles )
Next is to establish a point by measuring out a setback from fence to your building line. Taking just one side measure the setback from back of fence to the end of building lines in that particular angle, then come to the front and measure the setback also as given on your drawing plan .
After this go back to the rear or you may use the front as a point mark depending on which setback is more important to you in case the survey plan did not tally with what is the actual measurement on ground.
Measure the setback from fence establish this two points with pegs then put a rope to cross both pegs and make them form a right angle or 90 degrees , this is necessary because of it ease and most drawings are drawn to follow straight right angles. To determine if your rope are at right angle put a checker popularly called ‘square’ by bricklayers, this will direct you if you need to shift the other rope that can be varied since one is already fixed to form a base mark( i.e the rope running through two pegs from the rear to the front either on left side or the right side.
After establishing a right angle, do your measurement to correspond with what is on plan and then use the square at the other end to now establish the other two points. When establishing these points be conscious to place your peg at 1m or 3 ½ ft behind your building line i.e where blocks will actually pass through.
After this, nails peg at 3m interval round under the rope marking your building line, then nail tie rods (flat thin wood) on top round the entire area.
You are ready to start measuring and transferring what is on plan to the profile boards (flat thin wood on top of pegs) establish each room measurement by nails ( you require four nails at each measurement, two to establish the two sides of block you are going to place later on then the other two at both ends to serve as the points where you will excavate ,the length of this is usually three times the width of the block you are using that is if you are using a 6“ block then expect to excavate or dig a trench of 18” wide.
The type of digging also depends on the type of foundation recommended by your structural engineer.
Establish the depth based also on recommendation and you are ready to cast your concrete. After casting of foundation, use the nails on your profile board to determine where your blocks will follow from ground to complete foundation courses (note this is variation of application in raft and more complex foundation where reinforcements and concrete will be applied more.
Set your blocks 3,4 or more coaches / courses/ layers as recommended before casting your ground floor slab or oversite concrete or german floor.
November 10th, 2010 at 9:21 am
I have not seen your ideas and write ups on the issue of under ground building construction. can you refer me if there is any or put up a write up on this topic. Thanks. I must confess that you are a professional with great skills.
November 10th, 2010 at 4:25 pm
Your comment is noted and I will write on it as requested.
Thanks
December 28th, 2010 at 9:44 pm
You are wonderful, pls i need more information on foundation and excavation.thanks
August 21st, 2011 at 9:25 pm
i will luv to see pictures illustrating this.u are a real professional though i havent involve in a real constrution of building but want to more nd be able to do that.
August 23rd, 2011 at 12:18 pm
I am having a problem of setting out the house with basement garage
August 26th, 2011 at 2:18 am
Setting out, it compose of lind, rod, builder squre, hammer and nails etc
September 29th, 2011 at 9:01 am
I will like to see picture that illustrate your explanation
October 26th, 2011 at 8:31 pm
you Never specify if you are making use of builder square method or 3,4,5. And also if it is a new site where their is no existing building and if their is an existing building. Also getting the building line 4rm d centre of d road? Establishing a benchmark? transfering of level from road E.T.C you need to re-write ur atticle, but Goodwork anyway.
November 13th, 2011 at 10:05 pm
U r 2much
November 14th, 2011 at 4:34 am
I wil lik 2 no de standard size of room house
November 16th, 2011 at 12:28 pm
Good one, d explanations are quite understanding. I wil like to have a futher explanayion on setting out and foundation.
February 22nd, 2012 at 1:52 pm
I luv ur explanation but u did not specialized on a building or is it d same in al building even undaground pls i nid explanation
March 10th, 2012 at 1:00 pm
On setting out, Emma, pictorial illustrations would hav helped drive home the points graphically to a layman but to those of us professionals, u captured d basic principles of setting out for regular buildings. Thanks a lot.
March 12th, 2012 at 10:38 am
Your explanation is very good but should have a pictorial illustration. Also explain how to divide spaces within the profile board incase the person is not doing german floor.
March 24th, 2012 at 7:56 pm
pls i need more explanatory on setting out of a building and some factor about building
May 6th, 2012 at 1:39 pm
please how do I set out on a rock? whats goin to be my foundation depth? I need advice plz.
May 14th, 2012 at 8:23 pm
Your explanation is too scanty. Re-write and elaborate since your main target are the laymen.
May 18th, 2012 at 7:21 am
The explanaton need to throw more light on Type of construction, on the issue of establishing of the centre line of the building from fence, what about if the fence is a trapezodal one, or if the site is a virgin site( new construction). U also need to talk on hw to control the line using spirit level. Though, very nice article and very wimp language use
May 20th, 2012 at 9:35 pm
Rock itself is a foundation. We apply concrete at the foundation because we want to have a base that can sustain the weight of the building. And the rock is already doing thatyou don’t need any depth for the stability but for the surface wearing later on then if you can break 100mm I think is okay.